sch_topoi_sp {criticalpath} | R Documentation |
SP Serial or Parallel Topological Indicator
Description
Shows the closeness of a network to a serial or parallel graph. As the network becomes serial, the SP increase, until one; As the network becomes parallel, the SP decrease until zero.
Usage
sch_topoi_sp(sch)
Arguments
sch |
A schedule object. |
Value
A number between 0 and 1, inclusive.
See Also
sch_topoi_tf()
, sch_activities()
, sch_topoi_ad()
,
sch_xy_gantt_matrix()
, sch_relations()
, sch_topoi_la()
,
sch_add_activities()
, sch_add_relations()
.
Examples
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity( 10L, "a10", 3L, 12L) %>%
sch_add_activity( 11L, "a11", 3L, 12L) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
sch_topoi_sp(sch) # 0.4545455
[Package criticalpath version 0.2.1 Index]