sch_topoi_ad {criticalpath} | R Documentation |
Measures the distribution of the activities over the levels. If AD is approximately equal zero, each level has same numbers of activities. Otherwise, if AD is equal one, the quantity of each level is not uniformly distributed.
sch_topoi_ad(sch)
sch |
A schedule object. |
A number between 0 and 1, inclusive.
sch_topoi_sp()
, sch_topoi_la()
, sch_topoi_tf()
,
sch_xy_gantt_matrix()
, sch_add_relations()
, sch_add_activities()
,
sch_relations()
, sch_activities()
.
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity( 10L, "a10", 3L, 12L) %>%
sch_add_activity( 11L, "a11", 3L, 12L) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
sch_topoi_ad(sch) # 0.4