criticalpath: Critical Path Method R Implementation
Description
criticalpath
package is an R implementation of the
Critical Path Method (CPM). CPM is a method used to estimate
the minimum project duration and determine the amount of scheduling
flexibility
on the logical network paths within the schedule model. The flexibility is in
terms of early start, early finish, late start, late finish, total float and
free float. Beside, it permits to quantify the complexity of network diagram
through the analysis of topological indicators. Finally, it permits to change
the activities duration to perform what-if scenario analysis.
Details
With this package, you can calculate the following CPM parameters:
Schedule duration
Early start and finish date of each activity
Late start and finish date of each activity
Critical activities
Critical path
Total float and free float
Gantt Matrix
What-if scenario analysis
Topological indicators
Author(s)
Rubens Jose Rosa (rubens@rubensjoserosa.com), Marcos dos Santos (marcosdossantos@ime.eb.br), Thiago Marques (profestathimarques@gmail.com)
References
Csardi, G. & Nepusz, T. (2005). The Igraph Software Package for Complex Network Research. InterJournal. Complex Systems. 1695.
Project Management Institute (2017) A Guide to the Project Management Body of Knowledge (PMBOK Guide). Sixth Edition.
Project Management Institute (2017) PMI Lexicon of Project Management Terms: Version 3.2.
Vanhoucke, M. (2009) Measuring Time: Improving Project Performance Using Earned Value Management. Springer-Verlag US.
Vanhoucke, M. (2013) Project Management with Dynamic Scheduling: Baseline Scheduling, Risk Analysis and Project Control. Springer-Verlag Berlin Heidelberg.
Vanhoucke, M. (2014) Integrated Project Management and Control: First Comes the Theory, then the Practice. Springer International Publishing Switzerland.
See Also
On vignette package there are more information with examples about:
How to create a schedule:
Create a new schedule without any information.
Add activities and relations together to an schedule.
Add activities to a schedule.
Add relations to a schedule.
How to get schedule information:
Title
Reference
Duration
How to get activities properties:
Activity Properties.
Gantt Matrix.
How to change activities duration:
Change Activities Duration.
How to get relations properties:
Relation Properties
Successors and Predecessors.
How to get topological properties:
Topological Indicators.