schedule.pert {ProjectManagement} | R Documentation |
Schedule for deterministic projects
Description
This function calculates the duration of the project, the slacks for each activity, as well as the schedule of each activity.
Usage
schedule.pert(
duration,
prec1and2 = matrix(0),
prec3and4 = matrix(0),
PRINT = TRUE
)
Arguments
duration |
Vector with the duration for each activity. |
prec1and2 |
A matrix indicating the order of precedence type 1 and 2 between the activities (Default=matrix(0)). If value |
prec3and4 |
A matrix indicating the order of precedence type 3 and 4 between the activities (Default=matrix(0)). If value |
PRINT |
Logical indicator to show the schedule represented in a graph (Default=TRUE) |
Value
A list of a project schedule and if PRINT=TRUE a plot of schedule.
References
- burk
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Examples
prec1and2<-matrix(c(0,0,1,0,0,0,0,0,1,0,0,0,0,0,0,0,0,1,0,0,0,0,0,0,0),nrow=5,ncol=5,byrow=TRUE)
duration<-c(3,2,1,1.5,4.2)
schedule.pert(duration,prec1and2)