Safety cost of Failure for 0.4kV Board
Description
This function calculates safety consequences of failure
(cf. section 7.3, page 79, CNAIM, 2021). Safety consequences
of failure is used in
the derivation of consequences of failure see cof
().
Outputted in (DKK).
Usage
safety_cof_board_04kv(location_risk, type_risk)
Arguments
location_risk |
String Type Financial factor criteria for 0.4kV board
(cf. section D1.2.1, page 178, CNAIM, 2021).
Options: |
type_risk |
String. Asses Financial factor criteria for 0.4kV board
setting (cf. table 221, page 180, CNAIM, 2021).
Options: |
Value
Numeric. Financial consequences of failure for 0.4kV board
Source
DNO Common Network Asset Indices Methodology (CNAIM), Health & Criticality - Version 2.1, 2021: https://www.ofgem.gov.uk/sites/default/files/docs/2021/04/dno_common_network_asset_indices_methodology_v2.1_final_01-04-2021.pdf
Examples
safety_cof_board_04kv(
location_risk = "Default",
type_risk = "Default")