network_cof_tower {CNAIM} | R Documentation |
Network cost of Failure for Towers
Description
This function calculates network cost of failure for
all asset categories exclusive the assets EHV and 132kV transformers.
(cf. section 7.6, page 87, CNAIM, 2021). Network cost of failure
is used in the derivation of consequences of failure see cof
().
Usage
network_cof_tower(tower_asset_category, actual_load_mva, secure = T)
Arguments
tower_asset_category |
String The type of tower asset category
Options: |
actual_load_mva |
Numeric. The actual load on the asset |
secure |
Boolean If the asset is in a secure network or not |
Value
Numeric. Network cost of failure.
Source
DNO Common Network Asset Indices Methodology (CNAIM), Health & Criticality - Version 2.1, 2021: https://www.ofgem.gov.uk/sites/default/files/docs/2021/04/dno_common_network_asset_indices_methodology_v2.1_final_01-04-2021.pdf
Examples
network_cof_tower(tower_asset_category = "33kV Tower",
actual_load_mva = 15)
[Package CNAIM version 2.1.4 Index]