financial_cof_pillar_04kv {CNAIM} | R Documentation |
Financial cost of Failure for 0.4kV Pillar
Description
This function calculates financial consequences of failure
Financial consequences of failure is used in
the derivation of consequences of failure see cof
().
Outputted in DKK.
Usage
financial_cof_pillar_04kv(
type_financial_factor_criteria = "Asbestos clad",
access_factor_criteria
)
Arguments
type_financial_factor_criteria |
String Type Financial factor criteria for 0.4kV Pillar
(cf. section D1.2.1, page 178, CNAIM, 2021).
Options: |
access_factor_criteria |
String. Asses Financial factor criteria for 0.4kV Pillar
setting (cf. table 221, page 180, CNAIM, 2021).
Options: |
Value
Numeric. Financial consequences of failure for 0.4kV Pillar
Source
DNO Common Network Asset Indices Methodology (CNAIM), Health & Criticality - Version 2.1, 2021: https://www.ofgem.gov.uk/sites/default/files/docs/2021/04/dno_common_network_asset_indices_methodology_v2.1_final_01-04-2021.pdf
Examples
financial_cof_pillar_04kv(
type_financial_factor_criteria = "Asbestos clad",
access_factor_criteria = "Type A")